# 8.2 Lessons Learned and Post-Project Recommendations
The purpose of formal Lessons Learned and Post-Project Recommendations is to make it possible for project teams and the permanent organisation at large to **benefit from the experience acquired** during the project. It is also important to capture **ideas** and **recommendations for post-project work** relating to the operation of the product/service delivered, such as extensions, maintenance and ideas for **follow-up projects**.
**Note**: ==Improvement opportunities and Post-Project Recommendations should be captured== in some form as they come up ==during the project==. Otherwise, particularly in longer projects, the **ideas might get lost by the time the project reaches the Closing Phase**.
There are many benefits to formalising Lessons Learned and Post-Project Recommendations. When project team members **share their perspectives and provide feedback it provides useful insights** that, the requestor/client side can use to **manage post-project activities more effectively**.
![[Table 8.2 - Lessons Learned and Post-Project Recommendations - Key Participants.png]]
Because all projects are different, the Lessons Learned process **cannot be generic**. However, projects have common aspects, which can be discussed: project definition and planning (scope, deliverables, resources, etc.), project communication, project documentation, [[Change Control]], risk/issue management, decision- making, successes, mistakes and failures, team dynamics, overall project performance.
## Guidelines:
- The **Lessons Learned session** should be a **part of the Project-End Review Meeting** (though ==separate sessions could be organised at the end of project phases or major milestones==).
- It may be **preferable** to have the Lessons Learned session **facilitated by someone who has not been intimately involved in the project**, allowing the Project Manager (PM) to contribute as a participant.
- The **discussion should be structured** (using project phases, categories of activities, etc. as the organisational principle) to **cover every aspect** of the project.
- Improvement **ideas should be organised into groups** to help the team better visualize the appropriate next steps required to implement them.
- In some cases, it could make sense to address the Lessons Learned over **multiple sessions, each devoted to a different topic** (technical issues, business implementation, etc.).
- The Project Steering Committee (**PSC**) should be **invited** to the Lessons Learned session(s) as this will allow its members to transfer the Lessons Learned to other projects.
![[Table 8.2 - Lessons Learned and Post-Project Recommendations - RASCI.png]]
## Outputs
- Project-End Report (PM2 Template)