# 6.7 Transition Plan
The Transition Plan defines the **goals, prerequisites, activities and responsibilities** associated with transitioning **from the old (pre-project) to the new (post-project) state**. It seeks to **minimise the impact** of any **disruptions** on the business during the transition period, and to **facilitate the roll-out of project outputs** in a smooth and timely fashion, allowing them to be used efficiently and with no serious transition issues.
A successful transition is an **important prerequisite for achieving the planned project benefits**. All transition activities become part of the Project Work Plan and are scheduled and controlled as part of the overall project.
![[Table 6.7 - Transition Plan - Key Participants.png]]
## Inputs
- [[Business Case]] and Project Charter
- [[Project Work Plan]]
- [[Project Change Management Plan]]
- [[Business Implementation Plan]]
## Steps
1. Identify the roles and **responsibilities** linked to all aspects of the transition process.
2. Document **what must be completed** before the transition can start and finish.
3. Determine whether any **changes** need to be made to the physical (or virtual) environments within which the project outputs will be released.
4. Identify **possible business interruptions** and ensure that they are **communicated** to all affected stakeholders in a timely fashion.
5. Determine the **coordination**.
6. Determine the **needs** between various stakeholders (e.g. clients, users, etc.).
7. Ensure that **operational support and maintenance needs** are defined.
8. Define and schedule the **transfer of responsibility** for the deliverables from the Solution Provider (SP) to the Project Owner (PO)
9. Ensure that a **formal announcement** of the start and end of the transition is **planned**.
10. Include all **transition activities** in the Project Work Plan.
11. Ensure that the Transition Plan is **communicated** to the relevant project stakeholders.
![[Fig 6.9 Transition Plan inputs and main roles.png]]
![[Table 6.7 - Transition Plan - Related Artefacts.png]]
## Outputs
- [[Transition Plan]] (PM2 Template)
- Transition Checklist (setup) (PM2 Template)
___
Spanish Guide: [[6.7 Plan de Transición]]
<-- [[6.6 Deliverables Acceptance Plan]]
--> [[6.8 Business Implementation Plan]]