^ [[6.4 Project Work Plan]] # 6.4.3  Project Schedule The objective of this section of the Project Work Plan is to document the **dependencies** between tasks, pinpoint their **start and end dates**, and work out the **overall project duration**. Detailed scheduling can be done for the entire project upfront, or alternatively, worked out (in adequate detail) only for some early parts of the Executing Phase, and then progressively developed in full detail. The Project Manager (PM) **uses the schedule to authorise, coordinate and accept project work, and to monitor overall progress** (see Appendix C). ## Inputs - [[Project Charter]] - [[Project Work Plan]] ([[Work Breakdown]], Effort & Cost Estimates) ## Outputs -  Project Schedule (part of the Project Work Plan) ___ Spanish Guide: [[6.4.3 Cronograma del Proyecto]] <-- [[6.4.2 Effort & Cost Estimates]] --> [[6.5 Outsourcing Plan]]