^ [[6.4 Project Work Plan]] # 6.4.1  Work Breakdown The objective of this section of the Project Work Plan is to break the project down into **smaller and more manageable components such as deliverables, [[work package|work packages]], activities and tasks**. The breakdown has **multiple levels**, each with progressively more detailed deliverables and work. Taken together, these define the project output(s) and the work involved in producing them (see Appendix C). ## Inputs - [[Business Case]] - [[Project Charter]] - Project Requirements ## Outputs - Work Breakdown (part of the Project Work Plan) ___ Spanish Guide: [[6.4.1 Desglose del Trabajo]] <-- [[6.4 Project Work Plan]] --> [[6.4.2 Effort & Cost Estimates]]