^ [[6 Planning Phase]]
# 6.4 Project Work Plan
The Project Work Plan further elaborates the project scope and identifies and organises the project work and deliverables needed to achieve the project goals.
It establishes a basis on which to estimate the project’s duration, calculate the required resources, and schedule the work.
Once the tasks are scheduled, the Project Work Plan is used as a **basis for monitoring progress and controlling the project**. The [[Project Work Plan]] should be baselined but also **kept up-to-date during the life of the project** and ==capture all project related work as identified during planning phase or emerged during the [[executing phase]] (e.g. risks, issues, corrective actions etc.)==
![[Table 6.4 - Project Work Plan - Key Participants.png]]
## Inputs
- [[Business Case]]
- [[Project Charter]]
## Steps
The Project Work Plan is composed of **three parts**:
1. Develop the **[[Work Breakdown]]**: This provides a hierarchical breakdown (subdivision) of **all the work that must be done** to meet the needs of the customer. Outlining the tasks enables an estimation of their effort and cost requirements.
2. Develop the **Effort & Cost Estimates**: This outlines expectations of the resources needed and the time required to complete each project task, **within the constraints of resource availability and capabilities**. The effort and duration estimates are used to create the project [[schedule]] and [[budget]].
3. Develop the **Project Schedule**: This identifies **[[dependencies]]** between tasks, pinpointing their start and end dates, which is then used to establish the **overall project duration**.
![[Fig 6.6 Project Work Plan inputs and main roles.png]]
![[Table 6.4 - Project Work Plan - Related Artefacts.png]]
## Outputs
- [[Project Work Plan]] (see also PM2 Template)
___
Spanish Guide: [[6.4 Plan de Trabajo del Proyecto]]
<-- [[6.3 Project Stakeholder Matrix]]
--> [[6.4.1 Work Breakdown]]