# 6.1 Planning Kick-off Meeting
The Planning Phase starts with an official Planning Kick-off Meeting, the aim of which is to:
- ensure that **everyone understands the project scope**
- clarify the **expectations** of all key project stakeholders
- identify project **risks**
- **discuss the project plans**.
At this early stage, past experiences, and especially **Lessons Learned** from previous similar projects, will significantly help the project team.
This Planning Kick-off Meeting should be planned and run effectively as it is **critical that the project goals are well understood**. PM2 provides **templates** for the Meeting Agenda and the Minutes of Meeting (MoM).
![[Table 6.1 - Planning Kick-off Meeting - Key Participants.png]]
## Inputs
- Business Case
- Project Charter
## Steps
==Before the Planning Kick-off Meeting==:
1. **Plan** the meeting.
2. Draft the Meeting **Agenda** clearly indicating the points to be discussed.
3. **Send out the Meeting Agenda in advance**.
4. **Ensure the attendance of required participants**.
5. Address any **logistical** needs and prepare **documentation** or hand-outs for the meeting.
==During the Planning Kick-off Meeting==:
1. **Introduce** the meeting participants.
2. Ensure a **minute-taker** is identified to make notes identifying action items. These will be compiled and sent to participants after the meeting.
3. Walk the participants through the **Project Charter** so they understand the **project scope**.
4. Outline the **goals**, **expectations** and **activities of the Planning Phase** and discuss the planning **timeline**.
5. Describe and discuss the **project roles and responsibilities**.
6. Discuss the project **timeline**.
7. Discuss the overall **approach** to the project. This discussion can be a **brainstorming session** within the limits set by the Project Charter.
8. Discuss the project **plans needed** for the project. The final set of required project plans will be documented in the **Project Handbook**.
9. Discuss **risks**, **constraints** and **assumptions**.
10. Discuss or present any **project supporting tools** (with input from the Project Support Office, PSO).
11. Allow time for any other business (**questions & answers**).
12. **Summarise the discussion (decisions, actions and risks**).
13. Communicate the **next steps**.
==After the Planning Kick-off Meeting:==
1. Distribute the **Minutes of Meeting (MoM)** to the appropriate stakeholders (as identified in the Project Charter) **as soon as possible** (**within two business days** is considered as a best practice).
2. The Minutes of Meeting (MoM) should **include** a summary of project **issues** raised, **risks** identified, **decisions** taken and **changes** proposed. Note that the issues, risks, decisions and project changes should **also be recorded in the relevant logs**.
![[Fig 6.3 Planning Kick-off Meeting inputs - outputs and main roles.png]]
## Outputs
- Kick-off Meeting Agenda (see also PM2 Template)
- Minutes of Meeting (MoM) (see also PM2 Template)