# 4.9 Business Implementation Group (BIG)
The Business Implementation Group (BIG) sits on the **[[requestor side]]** and consists of **representatives of business and user groups**. Coordinated by the Business Manager (BM), it is responsible for **planning and implementing the business changes** that need to be made for the organisation to effectively **integrate the project deliverables** into its everyday work.
## Responsibilities:
- Analyses the **impact** of the project’s implementation **on ongoing operations**, existing **business processes**, staff and organisational culture.
- Participates in the design and **updating of affected business processes**.
- **Prepares** the affected business area for the **upcoming change**.
- Advises the Business Manager (BM) on the **organisation’s readiness for change**.
- **Embeds** the project **deliverables** **into business operations** and **implements** the **organisational change** activities that fall within the project’s scope.
## User Representatives (URs)
User Representatives (URs) r==epresent the interests of the project’s end-users and are part of the Business Implementation Group (BIG)==. It is important to **designate User Representatives (URs) and involve them throughout the project**, keep them **up to date with developments** and provide them with a **sense of ownership**. User Representatives (URs) help **define project requirements** and validate them at regular intervals, ensuring that the final deliverables are **fit for the business** purpose.
## Responsibilities:
- Help define the **business needs and requirements**.
- Ensure that the project specifications and deliverables meet the **needs of all users**.
- Review the **project specification** and **acceptance criteria** on behalf of the users.
- ==Communicate and prioritise user opinions in the Project Steering Committee (PSC)== and ensure that these opinions are taken into consideration when decisions are made whether or not to implement a proposed change.
- Participate in **demonstrations** and **pilot phases** as needed.
- Perform [[User Acceptance Test (UAT)|user acceptance tests]].
- **Sign off on user-related documents** (requirements document, deliverable acceptance testing, etc.).
- **Guarantee business stability** during the transition towards the new operational state.
___
Spanish Guide: [[4.9 Grupo de Implementación en el Negocio (GIN)]]
<-- [[4.8 Project Manager (PM)]]
--> [[4.10 Project Core Team (PCT)]]