# 4.12 RAM (RASCI) — Documenting Responsibility Assignments
The **[[Responsibility Assignment Matrix (RAM)]]** is a way of representing and clarifying the **roles and responsibilities for a given activity**. The RAM is ==also known as a RASCI table== (pronounced rasky), which stands for:
![[Table 4.12 - RASCI.png]]
**==Stakeholders should be reminded of their roles and responsibilities during the project.==** This Open PM2 guide includes a RAM **(RASCI) table for each artefact** in the Initiating, Planning and Closing Phases and for each of the activities in the Executing Phase and in Monitor & Control (**see Appendix E**).
## Example:
The RAM for the Standard PM2 roles involved in creating the Business Case document.
![[Table 4.12 - RASCI example.png]]
## Notes:
- Accountable: The Project Owner (PO) is accountable (S/he **provide adequate resources**).
- Responsible: The Business Manager (BM) is responsible for creating the Business Case.
- Supports: The Solution Provider (SP) and the Project Manager (PM) work with the Business Manager (BM) to develop the Business Case. The final responsibility, however, lies with the Business Manager (BM).
- Consulted: The Project Steering Committee (PSC) and User Representatives (URs) are consulted.
- Informed: The Appropriate Governance Body (AGB) will be **informed about the outputs or status of the task** (it will be provided with information).