# 4.11 Project Support Team (PST)
The Project Support Team (PST) is an **optional role** that consists of the people responsible for providing support to the project. Its **composition and structure depend on the needs of the project**. The Project Support Team (PST) is often composed of representatives from various **horizontal services or units**.
## Responsibilities:
- Provides **administrative support** to the project.
- Defines **requirements for reporting and communication**.
- **Administers Project Steering Committee (PSC)** meetings and drafts related reports.
- **Supports the Project Manager (PM) in planning, monitoring and controlling** the project.
- Advises on **project management tools** and administrative services.
- Manages the **project documentation** (versioning, archiving, etc.).
## Project Support Office (PSO)
The [[Project Support Office (PSO)]], ==also called Project Management Office or Project Office==, is an **optional structure** that can provide services to project teams such as the **application of the methodology** and use of the artefacts, information systems, governance, logistics and various support.
## Project Quality Assurance (PQA)
==Assigned by the Project Steering Committee (PSC)== and working **independently of the Project Manager (PM)**, the [[Project Quality Assurance (PQA)]] ensures the high quality of the project and its deliverables, by **reviewing processes and artefacts**, identifying non-conformities with the set quality standards and **recommending [[corrective actions]]**. This is an **optional role** in an organisation, ==reporting directly to the Project Steering Committee (PSC)==, and may take the form of either a group or individual staff member.
## Other
Depending on the project’s nature and characteristics, the Project Support Team (PST) can be further extended and include representatives from other departments/units, e.g. **Legal, Procurement, Data Protection**, etc.