# 4.10 Project Core Team (PCT)
The Project Core Team (PCT) comprises the **specialist roles responsible for creating the project deliverables**. Its composition and structure **depend on the project size and type** (e.g. IT project, policy development project, etc.) and is **defined by the Project Manager (PM) based on the project’s needs**.
## Responsibilities**
==Coordinated by the Project Manager (PM)==, the Project Core Team (PCT):
- Participates in developing the **project scope and planning project activities**.
- **Carries out project activities** based on the Project Work Plan and schedule.
- Produces project **deliverables**.
- **Provides** the Project Manager (PM) with information on the **progress of activities**.
- **Participates in project meetings** as needed and **helps resolve issues**.
- Participates in the **[[Project-End Review Meeting]]** during the collection of [[Lessons Learned]].
Aside from the specialist roles that create the project [[deliverables]], there are **two specific Project Core Team (PCT) roles** that deserve to be discussed in more detail from a project management point of view: the Contractor’s Project Manager (CPM) and the Project Manager Assistant (PMA).
## Contractor’s Project Manager (CPM)
The Contractor’s Project Manager (CPM) **leads the contractor’s staff working on the project**, planning controlling and **reporting on the production of outsourced deliverables**. **Working closely with the Project Manager (PM)**, the Contractor’s Project Manager (CPM) ensures that all work is carried out on time and to the agreed standards, guaranteeing the successful completion and delivery of subcontracted activities.
## Project Management Assistant (PMA)
**For large projects**, the Project Manager (PM) might find it useful to delegate some management tasks to an assistant. This Project Management Assistant (PMA) can work on a range of **coordination and supportive tasks as assigned by the Project Manager (PM)**, and acts as the Project Manager’s (PM) **backup** in meetings, etc. However, the ==Project Manager (PM) remains the person responsible== for all project management tasks and deliverables.
The Project Management Assistant (PMA) **may also be part of a [[Project Support Team (PST)]]** and assigned to the project.