ˆ. [[3.2 The PM2 Lifecycle]] # 3.2.6  Phase Gates and Approvals At the end of each phase, the project passes through a **review and approval gate**. This ensures that the project is reviewed by the appropriate people (i.e. the Project Manager (PM), Project Owner (PO), the [[Project Steering Committee (PSC)]] or other delegated role) before it moves on to the next phase. These checkpoints contribute to the overall project management **quality** and allow the project to proceed in a more **controlled** way. **The three PM2 phase gates are**: - RfP ([[Ready for Planning (RfP)|Ready for Planning]]): at the end of the Initiating Phase - RfE ([[Ready for Executing (RfE)|Ready for Executing]]): at the end of the Planning Phase - RfC ([[Ready for Closing (RfC)|Ready for Closing]]): at the end of the Executing Phase. ___ Spanish Guide: [[3.2.6 Puertas de Fase y Aprobación]] <-- [[3.2.5 Monitor & Control]] --> [[3.3 PM2 Phase Drivers and Key Artefacts]] ___ ![[👉 Quick links]]